    33While doing a POST operation on `/ticket/4597`, Trac issued an internal error.
    4 
    5 ''This test outlines the steps required to discharge the RBAT-2 installed on the VSTB.
    6 
    7 = RBAT2 Discharge Test
    8 
    9 == Setup
    10 Equipment Required:
    11 * ≥ 100W Power Resistor (Approx. 10 Ohms)
    12 * 44 Socket HD D-sub BOB Cable ST12024-3S for BCB2 P2 (See BOB Cable Configuration)
    13 * Volt Meter
    14 * Amp Meter
    15 * Set of hard wire with banana plugs and clips for resistor
    16 
    17 Steps:
    18 * Demate BCB2_J2 connector from the RPA
    19 * Install BOB cable at BCB2_P2 (Harness Side of W0104)
    20 * Install fluke amp meter in series into the battery circuit to measure the current discharging from battery.
    21 * Attach Hi side wires to RED SiDE of Pins 1, 2, 3 on BOB-1. Other ends of these wires to an empty Pin 1 on BOB-2.
    22 * Attach Lo Side wires to RED SIDE Pins 12, 13, 14 on BOB-1. Other ends of these wires to an empty Pin 2 on BOB-2.
    23 
    24 == Test Steps
    25 * Measure the voltage across Pin 1 and Pin 12 on RED SIDE of BOB-1
    26 {{{
    27 Expect ~30.4V
    28 }}}
    29 * Install Power Resistor across Pin 1 and Pin 2 of BOB-2. Monitor current draw on amp meter
    30 * Take Voltage measurements and Current Measurements every 10 seconds
    31 {{{
    32 Voltage should drop at a steady rate
    33 }}}
    34 * After 1 min discharging, remove the power resistor from BOB-2.
    35 * Measure the voltage across Pin 1 and Pin 12 on BOB-1
    36 {{{
    37 Voltage should drop by <1V
    38 }}}''